The biodiversity gain plan: what it must contain

The biodiversity gain plan is the document a developer submits after planning permission and before starting work, showing how the 10% net gain will be delivered. It must contain the completed metric, baseline and post-development habitat information, on-site enhancement and management details and the register evidence for any off-site units or credits. Development cannot lawfully begin until the planning authority approves it.

By BNG Sourced by Green Acres BNG specialists, reviewed by Mike Dungait, Managing DirectorPublished 3 October 2026Updated 3 October 2026Last checked against gov.uk: 3 October 2026

Key facts

  • Submitted after permission is granted and before development begins; the authority has eight weeks to decide.
  • Must use the statutory biodiversity metric and show at least 10% gain for each unit type present.
  • Off-site units must be allocated on the biodiversity gain site register before approval.
  • On-site habitat must be secured for 30 years by condition, Section 106 agreement or conservation covenant.
  • Draft gain plans are often accepted at application stage; the final plan follows permission.

Last checked: 3 October 2026

Office building beside a hedge and trees on a commercial development site

What goes in the plan?

SectionContent
Pre-development biodiversity valueMetric baseline, survey date, habitat plan, condition assessments
Post-development valueHabitat retained, created and enhanced on site, with target conditions
Off-site gainsRegistered site reference, units allocated by type, legal agreement
Statutory creditsAny credits purchased and the evidence that units were not available
HierarchyHow harm was avoided and on-site options considered (equal footing for minor development)
ManagementHow on-site habitat is secured and monitored for 30 years

Where do off-site units fit?

They are entered in the metric against the registered gain site and evidenced with the allocation confirmation. The allocation must be complete before the plan is approved, which is why sourcing should start well before permission. If you wait until the condition is live, the eight-week clock and scarce supply can collide.

Common reasons plans are refused

  • Metric errors, including the wrong multiplier.
  • Off-site units not yet allocated or of the wrong type.
  • On-site habitat with no credible 30-year management or funding.
  • Inconsistency between the plan and the approved drawings.

A gain plan timeline

StageWhat happens
ApplicationMetric and draft gain plan submitted with the planning application (draft often accepted)
PermissionGranted with the general biodiversity gain condition
SourcingOff-site units allocated on the register
SubmissionFinal gain plan submitted with allocation evidence
DecisionAuthority approves or refuses within eight weeks
CommencementDevelopment may begin once approved

Phased developments

Where permission is phased, a gain plan is submitted for each phase and off-site units are allocated phase by phase. Forward allocation agreements keep later phases covered without buying everything up front.

Who can submit the plan

The person who is to carry out the development, usually the applicant or their successor, submits the plan. A later purchaser of the site can submit it as the developer. Where the site is sold with permission, make the metric, surveys and any forward allocation part of the sale pack so the buyer can complete the plan.

Key takeaways

  • Submitted after permission, before development begins
  • Eight weeks for the authority to decide
  • Off-site units must be allocated before approval
  • Phased schemes submit a plan per phase

Frequently asked questions

Can I start enabling works before approval?

Generally no. Development must not begin until the plan is approved, apart from limited exceptions set out in the regulations.

Who approves the plan?

The local planning authority, within eight weeks of submission.

Does the plan cover NSIPs?

NSIPs use a biodiversity gain statement and plan secured through the development consent order.

Can the plan be amended?

Yes, with the authority’s approval, for example if phasing changes.

Can I submit the gain plan with the application?

A draft, yes. The final plan follows permission.

What if the authority does not decide in eight weeks?

The applicant and authority can agree an extension; the plan is not deemed approved by default.

Sources

Written by BNG Sourced by Green Acres BNG specialists and reviewed by Mike Dungait, Managing Director of Green Acres BNG, who has registered and manages two habitat banks. Indicative information, not legal or planning advice. Confirm with your ecologist and planning authority.

Related: BNG sourcing check, exemption checker, BNG unit prices, glossary, ecologist evidence checklist, how to buy off-site BNG units.

Need units for a live application?

Tell us your requirement and we'll start sourcing today.

Start the free sourcing check

One requirement, one point of contact, supply from across England.

01 Sourcing check stage one

We'll use your details to source BNG units for you. Your enquiry may be shared with Green Acres BNG and, where relevant, BNG providers. See our privacy notice.

Free for developers. Your details are only used to source your units.

Get BNG unitsCallback